Grand Hotel Imperial, Levico Terme: the numbers, the use, the method
Closed since 2024, two tenders without a buyer. Using public data, I look at why, which use could work and how one could proceed, step by step.
Photo: Mateus2019, 2020, via Wikimedia Commons, licence CC BY 3.0 DE, cropped.
The Grand Hotel Imperial in Levico Terme has been closed since 7 January 2024. Two tenders to sell it have found no buyer. On public data alone, the price per room looks lower than the Italian average. The cost of works in a historic building, however, can be far higher than the figure set in the tender. Before the price comes the question of use: a hotel, a health hub alongside the spa, an international hospitality school spread across the town, or a mix. Here I set out the numbers, the options and a method.
1. What we know
The Grand Hotel Imperial has been a hotel since 1900 and is tied to the Habsburg history of Levico (Libero, 2025). Patrimonio del Trentino spa, a company owned by the Autonomous Province of Trento, acquired it from the Province in 2013 to enhance its value (L’Adige).
The hotel closed on 7 January 2024. The closure affected 32 jobs (L’Adige).
The property offered in the December 2024 tender includes a four-star hotel with 80 rooms, 12 of them suites, and 160 beds; reception, bar, restaurant, meeting and banqueting rooms; a thermal wellness area, gym, solarium, indoor and outdoor pools; Villa Sissi, currently unused; covered parking, storage and a garden on the Habsburg park (L’Adige, 22 December 2024).
The tenders so far
- 2013. Patrimonio del Trentino acquires the building from the Province (L’Adige).
- November 2023. First tender, reserve price €10 million. The only bid was rejected in March 2024 (L’Adige).
- 7 January 2024. The hotel closes; the closure affects 32 jobs (L’Adige).
- December 2024. Second tender, reserve price €8.4 million, auction on 3 April 2025. The tender required works of at least €3.5 million over four years (exhibit 2). The price was payable 10% on completion and 90% within four years (L’Adige).
- 22 April 2025. The procedure closed with no formal bids. Some entrepreneurs had shown interest during site visits (Province press release).
- 5 May 2026. In the provincial council, the competent provincial minister spoke of no concrete prospect of a sale or lease on sustainable terms, and of a specialist study on the building’s potential, its possible uses and the sustainability of the investment (L’Adige, il Dolomiti).
- 20 June 2026. The mayor of Levico announced a new tender, for either management or sale (ilT Quotidiano).
The Levico context
- The Levico spa, whose building belongs to the Province and which has been privately managed since 2025, closed the 2025 season with more than 8,000 visits, 5,500 of them by residents of Trentino, and more than 10,000 people attending cultural events. Works worth over €1 million are planned for 2026 (Province press release, 27 October 2025; L’Adige).
- The spa company has bought two hotels, Villa Regina and Salus, to introduce a medical hotel offer (il Dolomiti, 2026).
- Levico hosts a campus of Trentino’s state hotel school. In 2021 the Province planned to extend the via Ziehl building with 6 classrooms, 6 workshops and a gym, for €4 million (Province press release, 9 April 2021).
- In 2022 a survey by the Trentino Landscape Observatory counted 143 hotel buildings in the province that had been closed for more than ten years. Levico had 8 of them, the largest total in the province by land area, 1.8 hectares, and by volume, 65,000 cubic metres (L’Adige, 28 July 2022).
2. Three calculations
These are my own calculations, based on public data. They are indicative only.
First: price per room. €8.4 million divided by 80 rooms gives €105,000 per room. Adding the €3.5 million of minimum works, €148,750. In the first half of 2026, 57 hotels with 9,343 rooms changed hands in Italy, at an average of about €170,000 per room (Cushman & Wakefield, Market Beat Italy). On paper, the Imperial costs less than the average.
Second: the works. The €3.5 million in the tender equals €43,750 per room. A Horwath HTL analysis of Italy, based on 50 hotel projects covering more than 5,570 rooms, puts the average cost of renovating hotels in historic buildings at €123,000 per room. Applied to 80 rooms, that average would give about €9.8 million. This is an order of magnitude: the real cost can only be known through a survey.
Third: the total. With a price of €8.4 million and works in line with the Horwath average, the investment would rise towards €18.2 million, about €228,000 per room, above the market average. At a 5% yield, close to prime yields for leased hotels in Italy (4.5-5%, Cushman & Wakefield), the building would need an indicative rent of about €910,000 a year, more than €11,000 per room.
What the numbers say. In my view the main issue is the uncertainty over the works, more than the price: every investor prices it in as a discount. Without a shared technical estimate, the gap between €3.5 million and €9.8 million weighs more than the reserve price.
3. Use before price
A building like the Imperial is worth what happens inside it, more than its square metres. At least four options are on the table.
A. Hotel. The historic use. Works and seasonality remain to be solved.
B. Health hub with the spa. The spa is investing in health, with the medical hotel and a largely local clientele. The Imperial could become its high-end accommodation. It would need a guaranteed supply of thermal water: L’Adige has reported that the hotel’s spa centre once ran out of its mineral water because of supply problems.
C. A distributed international hospitality school. A provincial councillor has suggested a school of advanced hospitality training in the Imperial (L’Adige, 5 May 2026). The idea can go further: classrooms, workshops and a training hotel in the Imperial, with students and staff housed in other buildings of the town that now stand empty. According to the Province, closed hotels can already house hotel staff (Province press release); use by students would need to be checked. A public benchmark: in Switzerland, EHL Hospitality Business School, founded in 1893, has 3,655 students (AACSB) and lists total academic fees of CHF 119,040 for its Bachelor for international students, covering the preparatory year and three years of study (EHL, 2026 fees). Levico would have a rare advantage: an existing hotel school and a historic grand hotel to serve as its laboratory.
D. A mix. Training hotel, school, health and events on the same site. It is the most complex formula, but it spreads revenue across twelve months.
4. Three scenarios
- Cautious. A new sale tender on similar terms. Uncertain works, seasonality, the risk of a third tender with no bids.
- Base. A long-term concession or lease. A provincial official has said that the Province and the municipality had asked for guarantees that public ownership would be kept for several years (L’Adige). A training hotel and an advanced hospitality school with a recognised academic partner. Property and operations kept separate.
- Optimistic. A project for the whole town. The Imperial at the heart of a distributed campus: an international school, health with the spa, events in the Habsburg park. Some of the 8 closed hotels come back to life as residences. Levico becomes a European case of regeneration.
A study, with numbers, will show which scenario holds.
5. How one could proceed: a seven-step path
These are general criteria, not comments on past procedures. In my experience this path reduces risk for the public owner, for investors and for the area. Each step produces a document that can be made public and support the procedure.
- Study of uses and demandOutput: Two or three comparable scenarios, with numbers
- Technical due diligenceOutput: Costed works plan by phase, minimum and maximum range
- Legal structureOutput: Concession, lease or sale scheme, with verifiable clauses
- Essential services agreed firstOutput: Agreements on thermal water, access, parking, park and spa
- Working groupOutput: Clear roles; property and operations separated by a contract
- Phased business planOutput: Phases, progressive openings, measurable indicators
- Public procedure and worksOutput: Complete proposal; public reporting on local benefits
Step 1. A study of uses and demand
Goal: choose the use before the price. Measure real demand: hotel guests by season, spa patients and visitors, students and teachers of a hospitality school, events in the Habsburg park. For each use: expected revenue, months of opening, partners needed, permits. Output: two or three comparable scenarios, with numbers.
Step 2. Technical due diligence
Goal: turn the uncertainty over works into a figure. Building survey, condition of systems, roofs and structures, fire safety and accessibility upgrades, heritage constraints and permit timelines. Output: a costed works plan by phase, with a minimum and maximum range. This is the document that is missing today and that, in my view, is worth more than any cut in the reserve price.
Step 3. The legal structure
Goal: choose the instrument that fits the public objective. If the owner wants to keep the property, a long-term concession or lease, with a rent that reflects the works and clear maintenance obligations. If it wants to sell, payment terms and guarantees consistent with a real construction programme. In every case, verifiable clauses on use, minimum opening and local benefits.
Step 4. Essential services agreed in writing first
Goal: remove the risks no investor can control. Thermal water, access, parking, relations with the park and the spa, governed by written agreements before the tender.
Step 5. The working group
Goal: bring the right skills to the table, each with a clear role. A hotel operator for management; an education partner, if the school is part of the project; the spa for health; restoration specialists; legal and tax professionals; one party that coordinates and is accountable for the project. Property and operations stay separate, with a contract between them.
Step 6. A phased business plan
Goal: a plan that works without miracles. Works by phase, progressive openings, revenue spread over twelve months, funding sources suited to a historic building, measurable indicators: jobs, days of opening, local suppliers, off-season stays.
Step 7. The public procedure and the works
Goal: reach the tender with a complete and transparent proposal, within the timing and forms the public owner sets. After the award: works by phase, a first partial reopening, public reporting on local benefits.
Each step has an owner, a timeline and a cost. Nobody jumps to step seven without doing step one.
One principle applies to every step: open procedures, clear rules, equal treatment, public documents. This also makes the operation easier to finance.
6. A working group
I have worked in real estate and private capital for over thirty years, with many hotel special situations. I have learned that historic buildings do not save themselves, and no single party saves them. They need different skills around the same table: hotel operators, schools and training institutions, restoration specialists, professionals, local associations and public bodies.
That is why I propose to build a working group to prepare a serious proposal ahead of the next public procedure. The group is open and non-exclusive. It involves no agreements on bids: everyone remains free to take part on their own. To public bodies I propose an open, public dialogue, in the forms and at the times the procedure provides, with no private channels.
The aim is to preserve the history of the Imperial and to strengthen Levico. It is what my work is about: «Bringing value back to life».
Frequently asked questions
How long has the Grand Hotel Imperial in Levico been closed?
The hotel closed on 7 January 2024, and the closure affected 32 jobs (L’Adige). Two sale tenders, in 2023 and 2024, found no buyer.
How much does the Grand Hotel Imperial cost?
The December 2024 tender set a reserve price of €8.4 million, with minimum works of €3.5 million over four years (L’Adige). The first tender, in 2023, started at €10 million.
Why did the tenders fail?
No detailed official reasons have been published. In the author’s view, the main factor is uncertainty over the real cost of works in a historic building, which can be far higher than the minimum works required.
What could the Imperial become?
The main options are a hotel, a health hub with the spa, a distributed international hospitality school, or a mix. The Province has announced a study of possible uses (L’Adige, il Dolomiti, May 2026).
What is a distributed hospitality school?
A model in which classrooms, workshops and a training hotel sit in one main building, while students and staff live in other buildings in the town. It can help fill the low season and bring empty buildings back into use.
How many closed hotels are there in Trentino?
A 2022 survey by the Trentino Landscape Observatory counted 143 hotel buildings closed for more than ten years, 8 of them in Levico Terme (L’Adige, 28 July 2022).
Sources
- L’Adige, «Grand Hotel Imperial, si ritenta la vendita: l’offerta minima chiesta adesso è di 8,4 milioni», 22 December 2024.
- L’Adige, «Grand Hotel Imperial chiuso da domenica scorsa, a casa 32 dipendenti», January 2024.
- Autonomous Province of Trento, press release of 22 April 2025 on the Grand Hotel Imperial procedure.
- L’Adige, 5 May 2026; il Dolomiti, 5 May 2026: question time in the provincial council.
- ilT Quotidiano, 20 June 2026: new tender announced in the municipal council.
- Autonomous Province of Trento, press release of 27 October 2025 on the Levico spa; L’Adige, October 2025.
- il Dolomiti, 2026: the spa company buys two hotels for a medical hotel.
- Autonomous Province of Trento, press release no. 847 of 9 April 2021: Levico hotel school.
- L’Adige, 28 July 2022: survey of closed hotels in Trentino.
- Libero, 2025: history of the hotel.
- Cushman & Wakefield, Market Beat Italy, first half of 2026.
- Horwath HTL, «Italy: Construction and renovation costs in hospitality».
- EHL Hospitality Business School, 2026 Bachelor fees; AACSB, EHL profile.
Legal notice. Personal content for general information, based on the public sources cited and updated to 27 November 2026. The calculations are the author’s and are indicative only: market averages do not replace a survey of the property. This text is not an offer to the public, an investment solicitation, legal, tax or investment advice, or real estate brokerage. The invitation concerns professional collaboration, not the raising of capital. The author is not a lawyer or a registered estate agent, holds no non-public information, does not act on behalf of any public body and may, like anyone, take part in public procedures. The parties mentioned have not reviewed the text. EHL and AACSB are cited for public data only and have no relationship with the author. The working group complies with competition and public procurement rules. To report errors: umberto@ronsisvalle.com; corrections will be made promptly.